Project Plan Post 3 of 7: Risk Analysis and Success Plan

Risk Analysis

Risk

Probability

(1-5)

Severity

(1-5)

Score

(P x S)

Action to Prevent/Manage Risk

Staffing

Retention

2

3

6

Second staff from partner institutions if necessary; maintain strong community and institutional links; integrate activities as far as possible into mainstream developments within the University.

Recruitment

2

3

6

A developer post needs to be filled. Recruitment will begin as soon as the grant letter has been received, if necessary staff may be seconded on a short-term basis or the development work carried out externally.

Organisational

Kultur II Group commitment

2

5

10

Regular meetings and workshops led by community needs; funding through call for case studies.

Project Management

2

3

6

Maintain strong team working; clear definition of responsibilities; forward monitoring of project plan; regular meetings.

Budget

2

3

6

Budget presentation is based on a realistic assessment of the needs of the project and its partners; regular review of resources and work in progress will be carried out by the Project Manager who will report any discrepancies to the Project Director and Project Advisory Group.

Technical

Technical viability

2

3

6

Ensure existing team have relevant experience; analyse technical requirements and solutions at an early stage in the project; review technical developments and user requirements regularly.

Legal

Copyright issues

2

3

6

Project outputs will be copyright cleared for submission to JISC and dissemination to the wider community; authors of case studies are required to clear copyright for any outputs.

Other

Researcher engagement

2

3

6

Maintain close links with institutions, departments and researchers, either directly or indirectly through nominated community representatives; ensure effective communication of project outcomes and methods; and ensure alignment of the project with the needs of the arts research community.

Sustainability

2

5

10

The project team are seconded from existing posts so the skills, knowledge and practice will both inform the wider community and be embedded within the sector. The adoption of a Project Sponsor will ensure the project outcomes are raised at senior levels both within institutions and across the sector. Technical enhancements, tools and services developed throughout the project will be made available to the JISC community freely. All case studies, workshop reports, toolkits and other project outcomes will be made publically available online for a period of at least three years by VADS.

Success Plan

The Kultivate project will produce a technical architecture report considering the findings of Josh Brown’s research into consortial repositories as applicable to┬áthe Kultur II Group. The project will also assess the sustainability of the Kultur II Group community and consider how this can be moved forward, producing a sustainability report reflecting on the findings of the environmental assessment.